Software for Window Manufacturers — Timber Window Production Management

Joinery Core Team · May 2026 · 5 min read
See Full FeaturesStart Free Trial →
Timber window manufacturing production software

Timber window manufacturing combines the precision of joinery with the volume of production work. Whether you make casement windows, flush windows, stormproof, or conservation units, every order goes through a defined process: timber selection, machining, assembly, weathersealing, priming, glazing, and finishing. When you have multiple orders at different stages — some in machining, some waiting for glass, some ready for delivery — keeping track without a system becomes a full-time job.

Beyond Sash Windows

While sash window companies deal with cords, weights, and spring balances, general window manufacturers face a broader range of products. Casement windows, tilt-and-turn, fixed lights, French doors, bifold doors — each with different hardware, different glazing, and different production requirements. Your software needs to handle this variety without requiring a different setup for every product type.

How window manufacturers use Joinery Core

Window manufacturing phases and worker assignments
Multiple window orders at different production stages — all visible on one timeline

Managing Glass Orders

Glass is often the longest lead item in window production. Sealed units from your glazing supplier can take two to four weeks. If you don't track glass orders against production schedules, you end up with finished frames sitting in the workshop waiting for glass — blocking space and delaying delivery. Joinery Core lets you track material deliveries against production phases, so you know exactly when glass is due and which order it's for.

In practice this is the Order Glazing phase. It comes after Timber in the standard phase order and shows on the Office page beside Order, Order Spray, Dispatch and Installation, with the production bars in the background, so the glass is ordered against the production plan. Made-to-size units go in as a One-Off Order, Pending until Delivered, or as a Bespoke line on the project's materials list, which never touches stock.

Compliance and Documentation

Window manufacturers deal with FENSA registration, Building Regulations compliance, energy ratings, and sometimes conservation area requirements. Joinery Core stores all project documentation — specifications, compliance certificates, energy calculations, drawings — attached to the relevant order. When the building inspector asks for documentation, it's one click away, not buried in a filing cabinet.

One window project through the five phases

Our window manufacturing software guide covers production planning in general. This post follows one timber window project, say eighteen casements for a builder, through the five production phases Joinery Core uses: Timber, Spray, Glazing, QC and Dispatch.

It starts in Pipeline. Add the lead with the project name, client, address and the type Doors/Windows, and tick the phases the job will need. When the deposit lands, press Pipeline Finished, choose WON and set the deadline: the system creates the project in Production and carries the phases across. On the Gantt chart (described in our joinery production planning post) set for each phase a start and end date, or a number of workdays and the system calculates the dates. Assign the joiners to Timber, the sprayer to Spray, the glazier to Glazing and the driver to Dispatch; each assignment appears in the Production Sheet and feeds labour time in Accounting.

Eighteen windows do not move as one lump. Phases can overlap: the timber phase is still running while the first frames are already in the spray booth. Materials go on the project's MAT list: timber, beads and ironmongery are reserved from Stock the moment you add them, and if the shelf cannot cover the order the line goes negative and tells you to order now (more in timber stock tracking). The Production Book, the PS button on the project, gathers the elements list, drawings, materials, Spray Pack and QC checklist into one A3 PDF for the workshop floor.

The mistake: promising a dispatch date the spray shop cannot keep

The builder asks when the windows arrive, and the date comes from the joinery bench: three weeks of machining and assembly, so three weeks. Nobody counted the spray booth. Every window takes several coats with drying time between them, and two other projects reach Spray in the same week. The frames stack up on the floor, the glazier waits because glazing comes after spraying, and the date goes.

Joinery Core does not stop you promising a date, but it shows the queue first. Pick the sprayer in the Employee filter at the top right of the Gantt and the chart shows only that person's projects, with their approved holidays as turquoise stripes, so a third project landing on Spray in the same week is visible while the windows are still in timber. Give the builder the date from that view, write what was agreed in the project's Client Comms log, and press Freeze Plan once the plan is handed over so the bars stop drifting. If the glass is late, unfreeze, move the bars, freeze again. More on this in our workshop scheduling post.

The Bottom Line

Window manufacturing is production-line joinery. Every order follows the same phases but with different specifications. You need software that handles this combination of consistency and variety — showing every order on one timeline, tracking every material, and giving you the cost visibility to protect your margins.

Frequently asked questions

Can the first batch of windows go to spray while the rest is still in timber?

Yes. Phases can overlap on the Gantt, and one phase can hold several segments with different people and dates, so the first ten frames can be in Spray while the joiners finish the other eight.

Do doors and sash windows need a different setup?

No. The same five phases serve a door order, and a sash window workshop can add its own steps as custom phases with a name and a colour. See our posts on software for door manufacturers and software for sash window companies.

What does the sprayer get for the job?

The Spray Pack in the Production Book: the instructions, colours and sheen for the project, printed with the rest of the book for the workshop floor.